explain the necessity and value of a schedule in controlling project work
0
votes
Project management-summative assessmens-further education and training certificate-project management-skill programme 7-project scheduling-us id 120382
asked
4 years
ago
by
anonymous
Please
log in
or
register
to answer this question.
0 Answers
Related questions
0
votes
0
answers
explain the necessity and value of a schedule in controlling project work
asked
7 years
ago
by
anonymous
0
votes
0
answers
the necessity of schedule in controlling project work
asked
1 year
ago
by
anonymous
0
votes
0
answers
You are the project manager at an industrial design firm. You expect to spend a total of $75,000 on your current project. Your plan calls for five people work on the project eight hours a day, five days a week, for four weeks. Acording to the schedule, your team should have just finished the third week of the project. When you review what the team has accomplished so far, you find they have completed 50% of the work at a cost of $35,000. Based on this information, calculate the Earned Value Numbers.
asked
8 months
ago
by
anonymous
project-management
0
votes
0
answers
The Statement of Work and the Requirements Document of the project planning process are two components of delivering a product or service. Define these components and their relevance to the planning process. What might these two planning components have in common? What are their differences? Explain your answer.
asked
9 years
ago
by
ecsanders
(
160
points)
0
votes
1
answer
Explain the concept of breakdown structures for a product, work and cost in simple terms