S-curve: how it is drawn and used to monitor the progress of project?

0
votes
How can i know that i am behind or ahead of the schedule using the information derived from the s-curve?
asked 9 years ago by aziztaha (200 points) edited 9 years ago by MaplePM

1 Answer

0
votes
The S Curve won't help you determine whether you are ahead of or behind schedule.  You need to use an earned value management process and critical path analysis to do that.  The S curve is used to support the probabilistic analysis that you can run to define the likelihood of finishing your project, or activities within your project on a given date.
answered 9 years ago by dsmcalis (1,570 points)