Welcome to Project Management Questions!

You can ask any question on Project Management and you can rest assured that real Project Managers will answer your shortly!

How to calculate the burn rate in project management?

+1
vote
What is the formula to calculate the burn rate in projects? And what do burn rates tell us about the project?
asked 10 years ago by anonymous

1 Answer

0
votes
To answer your second question first, the burn rate is an indication on how fast your project is spending money, a burn rate that is bigger than 1 means that the project is spending money faster than it should, a burn rate lower than 1 means that the project is spending money lower than it was expected, a burn rate of 1 means that the project is spending money as expected.

The formula for burn rate is the following:

Burn Rate = 1 / CPI = 1 / (BCWP/ACWP) = ACWP / BCWP = AC / EV
answered 10 years ago by TheManager (6,220 points)