What is a level 1 project schedule?

+1
vote
I'm hearing of 3 levels of project schedules: Level 1, Level 2, and Level 3. What are they? Is project level 1 an non-detailed project schedule, while level 3 is the most detailed?
asked 8 years ago by anonymous

1 Answer

0
votes
The level 1 project schedule is the very top level of the WBS, which the most breakable tasks, for example, in a website development project, a level 1 project schedule may consist of the following:

1- Design
2- Development
3- Integration
4- Testing

All of the above are level 1 tasks,

Level 2 for design will include the following

1.1 - PSD Design
1.2 - HTML Mockup

Level 3 is usually the most granular task (that cannot be broken further), and is assigned to a resource.
answered 8 years ago by humblepm (17,390 points)