How do you know that you have reached the most granular level of the WBS?

+1
vote
In a work breakdown structure how do you know that you have reached a point when no further breakdown is needed?
asked 9 years ago by anonymous

2 Answers

0
votes
No further breakdown is needed when there is sufficient information about the task to estimate the resources, costs, and timeline.
answered 8 years ago by sdcapmp (45,840 points)
0
votes
This depends on the type of the project, for huge projects I'd say the most granular level of the WBS (Level 3) should be a task of at two weeks (more or less). In small projects this can go down to just a day or half a day. It all depends. You should experiment with your projects and your resources yourself to know what level of detail you want in your WBS.
answered 9 years ago by TheProjectManager (2,630 points)

Related questions

+1
vote
1
answer
0
votes
2
answers
0
votes
1
answer
0
votes
1
answer
© 2010 - 2012 Project Management Questions - All Rights Reserved