1) Fill in the Earned Value table above to show PV, EV, AC, the cost variance (CV) and Schedule variance (SV) at each week through and including week 5.

0
votes
Task    $/Task    Week 1    Week 2    Week 3    Week 4    Week 5
A    $15,000     100%    100%    100%    100%    100%
B    $10,000    
100%    100%    100%    100%
C    $25,000    
75%    100%    100%    100%
D    $25,000    

40%    80%    100%
E    $10,000    

40%    100%    100%
F    $10,000    


30%    80%
G    $5,000    

40%    100%    100%
H    $15,000    



40%

ACWP    $6,500     $23,000     $54,000     $80,000     $90,000