What is the difference between fixed unit and fixed work in MS project?

0
votes
I am confused...

How do fixed units differ from fixed work in MS project. Please provide some examples...
asked 9 years ago by anonymous

1 Answer

0
votes
If it's a fixed unit task, then adding more resources to the task will shorten the task duration (unit is fixed, work and duration is variable). Usually a fixed unit task is the default setting.

If it's fixed work, then changing the task duration means that the workload on resources will increase (for example, from 70% to 90%).

You can read more about this here: http://www.projectmanagementquestions.com/1846/what-is-the-difference-between-fixed-work-and-fixed-duration
answered 8 years ago by anonymous