Is there a report to track tasks that should have been completed in ms project?

+1
vote
I have been trying to get a report to track tasks that should have been completed at day X. (similar to the one of "tasks that should have started")
asked 5 years ago by anonymous

1 Answer

0
votes
If I understand your question correctly, you will need to create a filter to do that. This has been discussed elaborately in this techrepublic article: http://www.techrepublic.com/blog/tech-manager/identify-late-tasks-with-this-custom-microsoft-project-filter/3309

In essence, you will first create a filter that will get you all the tasks that are not yet 100% completed.

Then, you apply another filter, which will return all the tasks that should have been finished on a certain date according to the original schedule baseline.

So, when you mix the two filters above, you will be getting all the tasks that are not yet completed but should have been finished by now.