I would like to change the project start date in MS Project, and there doesn't seem to be a simple and straightforward way of doing this. Can someone help me? And why did Microsoft strive to make it so hard for us to do this simple thing?
asked 7 years ago by anonymous

1 Answer

0
votes
This is for changing the start date (and finish date, if you want) in both MS Project 2003 and MS Project 2007:

- Open your project document
- Go to the "Analysis" toolbar
- Click on "Adjust dates"
- Change the start date to your liking

Doesn't the above seem simple and straightforward to you?

Note that you can always change the start date of a project in MS project, regardless of how far into the development of your project schedule you currently are.
answered 7 years ago by MaplePM (46,940 points)