Welcome to Project Management Questions!

You can ask any question on Project Management and you can rest assured that real Project Managers will answer your shortly!

Who does the project manager report to?

+1
vote
Who does the project manager usually report to? Please provide me with the answer if the organization the PM works for is:

- A functional organization
- A balanced matrix organization
- A projectized organization

Can the project manager report to more than one person at the same time?
asked 7 years ago by anonymous

1 Answer

0
votes
In a functional organization, the project manager usually reports to a functional manager (such as an IT Manager).

In a matrix organization, the project manager usually reports to one of the following:

- Program Manager
- PMO
- Project Sponsor
- Functional Manager

In a projectized organization, the project manager usually reports to the PMO, the Program Manager, or the Sponsor.

Yes, the project manager can report to more than one person at the same time. For example, in some organizations, the project manager reports to the PMO about the project management aspects of the project, he reports to the program manager about the status of the project, and he reports to the project sponsor about the conflicts/risks/issues that the project may encounter.
answered 7 years ago by MaplePM (46,940 points)