Terminal element in the WBS

0
votes
What is the terminal element in the Work Breakdown Structure? Is it the final leaf of the WBS (which is also known as the work package)? Please explain.

I know what a work package is, so if the terminal element is not the work package, then please give an example.
asked 8 years ago by anonymous

1 Answer

0
votes
A terminal element in the WBS is any leaf element. For example, if you have the following WBS:

1- Develop website frontend
1.1 - Create Database Structure
1.1.1 - Create tables

"Create tables" would be a terminal element. As you can see, it is the same as the work package. Some project managers/references state that a work package is a different than the terminal element, but they fail to explain how. I personally see no difference between the two.
answered 8 years ago by MaplePM (46,940 points)