how can i see the budegeted cost at a particular day for the base line schedule

0
votes
how can i see the budegeted cost at a particular day for the base line schedule, when i compare it with the actual. I assigned the baseline schedule, but the column for the BL budgeted cost this period shows empty, how can i sortout this issue? Thanks in advance
asked 6 years ago by anonymous

1 Answer

0
votes
If you have a work breakdown structure (WBS), you should be able to derive the numbers from it.
answered 6 years ago by sdcapmp (45,840 points)