Best practices for Gantt Charts

+1
vote
Can someone share some best practices to create Gantt charts? I've created Gantt charts for a long time now but I remember I started learning to create it by trial and error and I'm sure that there are some best practices when it comes to creating them.
asked 7 years ago by anonymous

1 Answer

0
votes
Some best practices that I follow:

- Don't break down tasks to a microscopic level before adding them to the Gantt Chart, your Gantt chart should be more or less a graphical representation of your WBS
- Try to have an up to date version of the Gantt Chart on the company's Intranet at all times.
- Have only one person update the Gantt Chart.
- Use dependencies and use them wisely (differentiate between lag and float / start to start and finish to finish tasks)
- Try not to change the default settings for the Gantt Chart in MS Project, for these settings are the most used
answered 7 years ago by FastProjectManager (10,100 points)

Related questions

0
votes
1
answer
asked 6 years ago by anonymous
+2
votes
1
answer
0
votes
1
answer
asked 6 years ago by anonymous
0
votes
1
answer
asked 6 years ago by anonymous
© 2010 - 2012 Project Management Questions - All Rights Reserved