Who writes the project charter?

0
votes
Who is the person who writes the project charter? Is it the project manager, or one of the stakeholders?
asked 9 years ago by anonymous

1 Answer

0
votes
The project manager is the person who writes the project charter, either solo or in concert with the project sponsor. The project sponsor is the one who signs off (approves) the project charter.
answered 9 years ago by humblepm (17,390 points)